1.Read the documents before you measure
The plans show where tile goes. The other documents decide what it costs. Check:
- Finish schedule and legend: every tile code, size, color, finish and grout.
- Specifications: mortar and grout type, waterproofing, movement joints, attic stock, mock-ups and warranty.
- Elevations and details: wall tile height, base type, niches, outside corners and trim profiles.
- Addenda: a late finish change can replace a tile code you already priced.
- Schedule: night work, phasing and how many trips you have to make.
If the finish schedule and the elevations disagree, send a question before bid day. If there’s no time for an answer, state in your bid which one you priced.
2.Take off each tile code on its own
Keep floor, wall, base and trim apart, because each has its own waste and its own pace.
- Floor and wall tile: square feet, by tile code.
- Base, bullnose and cove: linear feet, plus inside corners, outside corners and end caps by the piece.
- Metal trim: linear feet, converted to full lengths, plus corners and connectors.
- Waterproofing and crack isolation: square feet, including the height it turns up the wall.
- Transitions and thresholds: each doorway.
3.Add waste, then round up to full cartons
Waste depends on the pattern, tile size and number of cuts. Common starting points:
Starting waste by layout
- Straight lay
- About 10%
- Diagonal (more in small or cut-up rooms)
- About 15%
- Herringbone
- About 15–20%
Large tile in a small room runs higher, since each edge cut can throw away most of a tile. Add the waste to the square feet first and convert to cartons second. Attic stock goes on top: it stays with the owner, so it can’t also cover your breakage.
4.Price the setting materials by coverage
Mortar use changes a lot with the trowel. For one large-tile mortar, Mapei’s data sheet gives these approximate yields per 50 lb bag:
Coverage per 50 lb bag
Mapei Ultraflex LFT, approximate.
- 1/4″ × 1/4″ × 1/4″ notch
- 85–95 sq ft
- 1/4″ × 3/8″ × 1/4″ notch
- 65–75 sq ft
- 1/2″ × 1/2″ × 1/2″ notch
- 40–50 sq ft
A floor that moves from a 1/4″ notch to a 1/2″ notch needs about twice the mortar. Read the yield for the product in the spec, and use the low end if the substrate is rough. For grout, use the maker’s calculator with your tile size, thickness and joint width.
5.Decide who pays for a floor that isn’t flat
Under ANSI A108.02, the substrate for tile with any edge 15″ or longer must be within 1/8″ in 10 ft and 1/16″ in 24″. Tile with all edges shorter than 15″ is allowed 1/4″ in 10 ft. A 12×24 tile triggers the tighter number, and many slabs miss it.
Pick one approach and write it down: include a stated amount of prep, exclude it, or give a unit price per bag of patch or leveler. With a unit price, both sides know the cost before anyone sees the slab.
6.Estimate labor in hours
Square-foot labor rates hide the difference between an open floor and a restroom full of cuts. Estimate hours by task, then multiply by a loaded rate: wage plus payroll taxes, workers’ comp, liability insurance and benefits. Add time for:
- layout, protection and moving material from the dock to the room
- small tile, tall walls, mosaics and epoxy grout, which all slow a crew down
- return trips, night shifts, parking, travel and lodging
- punch list and closeout paperwork
On prevailing-wage jobs, use the published rate for the county and classification. Your own finished jobs are the best source: divide square feet set by hours paid, and keep that number by tile size.
7.Add overhead and profit
Overhead is the cost of being in business: office, trucks, estimating time, software and insurance not already in your labor rate. Divide a year of overhead by a year of direct job cost to get your percentage. Profit comes after that.
Watch the difference between markup and margin. A 30% markup on cost is a 23.1% margin on the price. If you want a 30% margin, divide your cost by 0.70.
Worked example: commercial restroom tile
Every rate here is made up to show the method. Swap in your own quotes, hours and percentages.
- Labor$13,632.00
- Materials$10,668.20
- Freight and tax$1,090.09
- Overhead$3,046.83
- Profit$2,843.71
Materials
Measured quantity, plus waste, rounded up to what you order.
| Item | Cost |
|---|---|
| Floor tile, 12×24 porcelain640 sq ft + 10% waste 704 sq ft × $4.20 | $2,956.80 |
| Wall tile, 4×12 ceramic1,120 sq ft + 10% waste 1,232 sq ft × $3.10 | $3,819.20 |
| Cove base180 lin ft + 10% waste 198 lin ft × $6.50 | $1,287.00 |
| Metal edge trim150 lin ft + 10% waste 21 pcs (8 ft) × $22.00 | $462.00 |
| Mortar, floor (1/2″ notch)640 sq ft + 5% waste 17 bags × $34.00 | $578.00 |
| Mortar, wall (1/4″ × 3/8″ notch)1,120 sq ft + 5% waste 19 bags × $34.00 | $646.00 |
| GroutNo waste added 14 bags × $38.00 | $532.00 |
| Waterproofing membrane320 sq ft + 10% waste 352 sq ft × $1.10 | $387.20 |
| Materials total | $10,668.20 |
Labor
Hours by task, at a $48.00 loaded rate.
| Task | Hours | Cost |
|---|---|---|
| Mobilize, protect, layout | 16 | $768.00 |
| Floor prep and waterproofing | 24 | $1,152.00 |
| Set floor tile | 56 | $2,688.00 |
| Set wall tile | 112 | $5,376.00 |
| Base and trim | 28 | $1,344.00 |
| Grout, caulk, clean | 40 | $1,920.00 |
| Punch list and closeout | 8 | $384.00 |
| Labor total | 284 | $13,632.00 |
From cost to price
- Materials
- $10,668.20
- Freight
- $450.00
- Sales tax6% of materials
- $640.09
- Labor284 hours × $48.00
- $13,632.00
- Direct cost
- $25,390.29
- Overhead12% of direct cost
- $3,046.83
- Profit10% of cost plus overhead
- $2,843.71
- Bid price
- $31,280.83
The 12% and 10% markups together leave a 18.8% gross margin, and overhead is paid out of that. Sales tax rules for contractors vary by state, so confirm yours with your accountant.
BidPaid counts labor as part of your gross profit, because your crew is paid out of it. It shows a higher margin for this same bid.
8.Write inclusions and exclusions
Plenty of bid disputes start with something neither side wrote down. Cover these:
Inclusions and exclusions
- Tile codes and areas included, and the plan date and addenda you priced
- Floor prep, leveling, demolition and disposal
- Waterproofing, crack isolation and movement joints
- Sealing, final cleaning and protection after you leave
- Attic stock, mock-ups and samples
- Working hours and number of mobilizations
- Sales tax, freight and how long the price is good for
- Retainage and payment terms
9.Check it before you send it
- Every tile code on the finish schedule appears in your bid or your exclusions.
- Wall square feet look right against floor square feet for that room type.
- Quotes are current and cover freight and lead time.
- Total labor hours make sense for your crew size and the schedule.
- The price per square foot is close to similar jobs you’ve finished.
Sources
- Mapei Ultraflex LFT product data (mortar coverage)
- Laticrete TDS 164 (substrate flatness for large tile, and lippage)